156
Story points delivered
across 30 stories, 6 sprints
Release health snapshot 01. Report Date: 01-08-2026
iaci.tech is now live on Vercel + Supabase. [IW-85]
156
Story points delivered
across 30 stories, 6 sprints
0
Sev 1/2 defects
in delivered scope
~12%
Lower annual hosting cost
$40.94 annual reduction
~99.96%
Faster release-note publishing
~3 hrs → ~4 seconds
01
Cost impact
02
Public API performance
Response times ranged 0.86s–2.73s across a sample of public endpoints, typically settling under 1.3s after the initial connection.
03
Monitoring
6 requests rejected since cutover — all automated/non-visitor traffic caught by origin verification, not real errors.
Latest 24-hour platform snapshot: 174 requests processed, 0 warnings, 0 errors.
Verification approach: manual functional testing across EN/FR for each shipped feature, including API and edge-case checks, combined with live post-launch monitoring.